JAKARTA MRT TARGETED OPERATING IN MARCH 2019
페이지 정보
작성자 Aditya 작성일 17-03-02 13:23 조회 4,209 댓글 0본문
Workers dismantle four Tunnel Boring Machine (TBM) which has completed drilling an underground tunnel along the 1.400-2.600 meters, for the Jakarta Mass Rapid Transit (MRT) Phase 1 project. Overall, the Jakarta MRT project Phase 1 with a path length of 16 kilometers from Lebak Bulus (South Jakarta) to Hotel Indonesia roundabout (Central Jakarta) has reached 62%, with details of underground structure of 80%, overpass structure 50%, and is targeted to be ready to operate in March 2019. (JakartaBizWeekly/Aditya)