JOKOWI'S MEGA PROJECT IN THE MIDST OF ECONOMIC SLOWDOWN > 포토뉴스

본문 바로가기

팝업레이어 알림

팝업레이어 알림이 없습니다.
사이트 내 전체검색

포토뉴스 JOKOWI'S MEGA PROJECT IN THE MIDST OF ECONOMIC SLOWDOWN

페이지 정보

작성자 Aditya
댓글 0건 조회 2,813회 작성일 2019-11-05 16:22

본문

Workers assemble electricity installations on high voltage towers in the 35,000 Mega Watt electricity project in Jakarta, Tuesday, November 5, 2019. The slipping of Indonesia's economic and investment targets has made President Joko Widodo's ambitious project slow down. The megaproject, which was launched in 2015 and is planned to be completed in 5 years, is currently only realizing 3,600 Mega Watts, making the government have to reschedule the completion of the project in 2022-2023. (JakartaBizWeekly/Aditya)

댓글목록

등록된 댓글이 없습니다.


Copyright © PT. Inko Sinar Media. All rights reserved.